Chapter one
Clay tile meeting flint in Lyminster
The appraisal makes flint the dominant wall and clay tile the prevailing roof covering, so the junction between them deserves the closest look.
Arun District Council's conservation area appraisal says flint is the dominant walling material in Lyminster, and that the prevailing roof covering is clay tile, with slate also present on some buildings. The same record lists flint, red brick, render, tile hanging and weatherboarding among the village's walls, and calls flint boundary walls one of its most distinctive features. For a roofer, a flint village means a great many junctions where a roof ends against a wall, and each junction is a place where rain can find a way in.
At a glance
- Flint is the dominant walling material
- Clay tile is the prevailing roof covering, with some slate
- Flint boundary walls are among the village's most distinctive features

1.1 Flashings against flint
Flashing is lead strip used to seal the edge of a roof against a wall. Against flint it is tucked into a mortar joint, and flint's uneven face gives less margin than brick would. If the mortar behind the lead has crumbled, or the lead has pulled clear, rain tracks down the masonry and appears on an inside plaster surface a good distance from the fault. Code 4, which is 1.80 mm thick, is the usual weight for general flashing, according to Leadworx. We repoint the joint before new lead goes in, because dressing fresh metal into failing mortar only repeats the problem. Old masonry shifts, so a flashing that fitted tightly once can open at the joint, and we test each one by hand as well as by eye. Our slate roofing page describes the lead details that go with slate.

1.2 What clay tile and slate each ask for
A clay tile hangs from a batten on its nibs and sheds water through the overlap of its courses. Slate is nailed or hooked, and Cupa notes that BS 5534 indicates a minimum pitch of 20 degrees for natural slate at moderate exposure, with hook fixings not to be used below 25 degrees. MyBuilder gives 80 to 100 years or more for a slate roof that is well installed, but the fixings beneath often tire sooner than the slate does. Slipped slates are commonly a nail problem, not a slate problem, so we lift a few to read the nails and battens before recommending anything. Where the covering is sound and only the fixings have failed, re-hanging it on new battens keeps the original roof, and the photographs we take set the evidence in front of you.
Tracing a leak where tile meets flint
- Inside We map the stain and damp timber from the loft, then work outwards.
- Joint The mortar behind the lead is tested for crumbling and gaps.
- Lead The flashing is checked for splits, lifting and pulled edges.
- Photographs Every fault gets a photograph of your own roof for the written quote.